In terms of electrical installations, was provided a distribution network internal medium voltage consists of 6 transformer stations with a total installed capacity of 13MVA, there is still a priority network NO BREAK with an installed capacity of 1MVA. With regard to telecommunications building will be equipped with 2 DATA CENTER equipped with building blocks capable of storage, backup, virtualization and connectivity.
In partnership with the Portuguese Group of Frio and Soares da Costa, Acribia worked in the preliminary design of HVAC and refrigeration installations. In partnership, latest, with Pedro Sousa - Projectos e Gestão de Instalações Técnicas, Ltd. Acribia, also worked in conception of the facilities HVAC, refrigeration, water, sewer, fire network and centralized technical management and monitoring of respective work.
Location: S. Julião do Tojal - Portugal
Road Tunnel, with high level of complexity conception of drainage system. The tunnel, as also equipped with advanced security systems of detection and extinguishing fires.
Location: Almada - Portugal
Construction of ASA Air Traffic Control Building.
Estimated Cost: € 3.370.000
Location: Républica de Cabo Verde
Process of high technical complexity, which provides a turnkey solution for implementing an NREN with links to 10 Gbit/s. With an approximate length of 6.000 km the network is designed to serve a population of 2.55 million users. The conception of this project includes the development of all applicational component to allow communication between multiple locations, systems and services.
In this section with a length of 16 km, were performed work on upgrading of electrical infrastructure and telecommunications as well as redefining the lighting of several access nodes of the route.
Location: Lousã - Portugal
Recreational park with an area of 28.300 m2, comprising a support building, amphitheater and several playgrounds. In this process there was a detailed study of the system of stormwater runoff, to prevent possible flooding of the land due to the high irregularity of the pavement.
Location: Almada - Portugal
Requalification of Railway Station Building (Rossio).
Estimated Cost: € 7.000.000
Location: Lisboa - Portugal
Year: 2004
Freeway Road Enlargement – IC19 (alfragide/Queluz): Management and supervision of sontruction site works, including health and safety coordination.
Estimated Cost: € 6.710.000
Location: Lisboa - Portugal
Year: 2000 - 2001
Foundations and Structures Designs.
Location: Estarreja - Portugal
Year: 1994 - 1995
Foundations, Structures and Plumbing Designs.
Estimated Cost: € 25.000.000
Location: Ermesinde - Portugal
Year: 1995 - 1997
Foundations, Structures and Plumbing Designs.
Estimated Cost: € 40.000.000
Location: Boavista - Portugal
Year: 1998 - 2004
Land Movement Design; Road and Hydraulic infrastructures designs; Geotechnical works design; Solid waste removal plan; Road Node design.
Estimated Cost: € 21.000.000
Location: Porto - Portugal
Year: 2001 - 2004
Landscape Engineering Design; Hydraulic infrastructures design; Foundations, structures and electrical designs; Safety and health plan.
Estimated Cost: € 300.000
Location: Braga - Portugal
Year: 2001 - 2004
Management and Quality Control.
Estimated Cost: € 2.200.000
Location: Leixões - Portugal
Year: 2001 - 2003
Road and Hydraulic Infrastructures Designs; Road signs plan design.
Estimated Cost: € 1.300.000
Location: Viseu - Portugal
Year: 2001 - 2004
Foundations, Structures and Plumbing Designs.
Estimated Cost: € 3.000.000
Location: Vila Nova de Gaia - Portugal
Year: 2001 - 2003
Hydraulic Infrastructures Design.
Estimated Cost: € 400.000
Location: Vila Nova de Gaia - Portugal
Year: 2002 - 2003
Management and Quality Control.
Estimated Cost: € 1.500.000
Location: Aveiro - Portugal
Year: 2003
Management and Quality Control; Safety and health coordination.
Estimated Cost: € 1.500.000
Location: Porto - Portugal
Year: 2004
Engineering Design.
Estimated Cost: € 5.300.000
Location: Vila Nova de Gaia - Portugal
Year: 2004 - 2006
Demolition Plan; Management and Quality control.
Estimated Cost: € 1.000.000
Location: Coimbra - Portugal
Year: 2005
Landscape Engineering Design; Hydraulic infrastructures design; Foundations, structures and electrical designs; Safety and health plan.
Estimated Cost: € 3.833.000
Location: Viana do Castelo - Portugal
Year: 2005 - 2009
Management and Quality Control; Safety and health coordination; Environmental management in construction.
Estimated Cost: € 500.000
Location: Aveiro - Portugal
Year: 2005 - 2006
Foundations, Structures and Plumbing Designs; Management and quality Control; Safety and health plan and coordination.
Estimated Cost: € 600.000
Location: Porto - Portugal
Year: 2005 - 2008
Safety and Health Coordination.
Location: Alfarelos - Portugal
Year: 2005 - 2006
Management and Quality Control; Safety and health coordination.
Estimated Cost: € 2.000.000
Location: Alto do Lumiar - Portugal
Year: 2006 - 2007
Landscape Engineering Design; Hydraulic infrastructures design; Foundations, structures and electrical designs; Safety and health plan.
Estimated Cost: € 510.500
Location: Matosinhos - Portugal
Year: 2007 - In course
Facades Design.
Construction Area: 40.000 m2
Estimated Cost: € 45.000.000
Location: Dublin - Irlanda
Year: 2007 - 2009
Landscape Engineering Design; Road and hydraulic infrastructures designs; Road signs plan design.
Location: Vila Nova de Gaia - Portugal
Year: 2007
Infraestructures Designs.
Location: Vila Nova de Gaia - Portugal
Year: 2007 - In course
Engineering Design.
Estimated Cost: € 600.000
Location: Santo Tirso - Portugal
Year: 2007 - In course
Safety and Health Coordination.
Estimated Cost: € 1.500.000
Location: Maia - Portugal
Year: 2008
Management and Quality Control; Safety and health coordination; Environmental management in construction.
Estimated Cost: € 11.500.000
Management and Quality Control; Safety and health coordination; Environmental management in construction.
Estimated Cost: € 11.200.000
Management and Quality Control; Safety and health coordination; Archaeological monitoring.
Construction Area: 799 m2
Estimated Cost: € 700.000
Location: Porto - Portugal
Year: 2009 - 2010
Demolition Plan; Management and Quality control; Safety and health coordination.
Estimated Cost: € 50.000
Location: Lisboa - Portugal
Year: 2010
Architetcural and Engineering Designs Checking.
Estimated Cost: € 2.054.403
Location: Lisboa - Portugal
Year: 2010 - 2011
Expansion of Lisbon Airport Transfer Terminal.
Estimated Cost: € 1.637.000
Location: Lisboa - Portugal
Placement of Metal Safety Rails and Side protection networks on the northern overpass of the 25 de abril bridge.
Estimated Cost: € 1.294.000
Location: Lisboa - Portugal
Rehabilitation of the Kuito-Andulo road.
Estimated Cost: 88.000.000 USD
Location: Kuito-Andulo - República de Angola
Water Supply project for the city of Soyo
Estimated Cost: 7.350.000 USD
Location: Soyo - República de Angola
Water Supply project for the city of Cabinda
Estimated Cost: 5.500.000 USD
Location: Cabinda - República de Angola
Water supply project for the city of Lândana
Estimated Cost: 6.715.000 USD
Location: Lândana - República de Angola
Airport Expansion (Faro)
Estimated Cost: € 15.000.000
Location: Faro - Portugal
Year: 1988 - 1989